[RUH] Storage Cluster Maintenance - Stage 2
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you regardless of the 6 hours extension of Stage 2, the planned work for that stage was not completed. We will continue with the tasks during Stage 3, which is scheduled for:

Date and Time Maintenance Starts: 2023-09-12 15:00 UTC ; 2023-09-12 18:00 AST
Posted Sep 12, 2023 - 09:49 UTC
Update
CloudSigma would like to inform you that the maintenance works will be extended with additional 2 hours.
Posted Sep 12, 2023 - 05:28 UTC
Update
CloudSigma would like to inform you that the maintenance works will be extended with additional 2 hours.
Posted Sep 12, 2023 - 01:44 UTC
Update
CloudSigma would like to inform you that the maintenance works will be extended with additional 2 hours.
Posted Sep 11, 2023 - 23:54 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 11, 2023 - 15:00 UTC
Scheduled
CloudSigma would like to inform you that we are planning to perform a scheduled maintenance of our storage cluster in the Riyadh cloud location. The maintenance aims at upgrading the underlying software in our storage cluster. The actual works are planned to take no longer than 9 hours in total.

IMPACT:
There will be no impact on any of the existing servers, drives, or networking, other than a slight increase in the I/O operations for the duration of the maintenance window.
Posted Sep 04, 2023 - 00:08 UTC
This scheduled maintenance affected: Riyadh Cloud.