[SJC] PDUs re- cabling
Scheduled Maintenance Report for CloudSigma
Completed
The scheduled maintenance has been completed.
Posted Aug 06, 2014 - 20:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 06, 2014 - 18:00 UTC
Scheduled
CloudSigma would like to inform you that we will be performing an upgrade to PDUs running compute and storage nodes in our cloud. Based on internal testing the lowest risk with minimal impact methodology has been found to be as follows:

(1) Prepare the PDUs for upgrade
(2) Map additional cables to the free sockets
(3) Replace legacy equipment
(4) Run the upgrade

This will prevent upgrade our PDUs with to ones with additional management capabilities which will be used for higher uptime and greater operational visibility moving forward. This upgrade is not expected to be service affecting.

All support activities will be conducted under the direct supervision of CloudSigma’s operations staff.

IMPACT:
During the maintenance no disruptions on customer’s infrastructure are expected.

Please accept our sincere apologies for the caused inconveniences.

Thank you for your understanding.

While it is important for CloudSigma to perform maintenance such as this to ensure the quality of our services, we try to do everything possible to minimize any inconvenience to our customers. We appreciate your patience and welcome any feedback.
Posted Jul 28, 2014 - 17:04 UTC