[DUB] Power Maintenance
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you that the scheduled maintenance of our power supply units in the Dublin cloud location has been completed. The actual works took 8 hours.

All support activities were conducted under the direct supervision of CloudSigma’s DevOps staff.

IMPACT:
The maintenance was non-service affecting and clients did not experience any interruptions in the service.

While it is important for CloudSigma to perform maintenances such as this to ensure the quality of our services, we do everything possible to minimize any inconvenience to our customers. We appreciate your patience and welcome any feedback.

Contacts:
If you have any questions in regards to this email, please contact our support department via our live chat at https://ec.servecentric.com/ui/4.0/ and/or email support@cloudsigma.com
Posted Sep 05, 2019 - 15:13 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 05, 2019 - 05:45 UTC
Scheduled
CloudSigma would like to inform you that we are planning to perform scheduled maintenance of our power supplies in the Dublin cloud location. The actual works are planned to take no longer than 12 hours and 15 minutes.

All support activities will be conducted under the direct supervision of CloudSigma’s DevOps staff.

IMPACT:
The maintenance is non-service affecting and clients should not experience any disturbance in the service.

While it is important for CloudSigma to perform maintenances such as this to ensure the quality of our services, we do everything possible to minimize any inconvenience to our customers. We appreciate your patience and welcome any feedback.

Contacts:
If you have any questions in regards to this email, please contact our support department via our live chat at https://ec.servecentric.com/ui/4.0/ and/or email support@cloudsigma.com
Posted Sep 04, 2019 - 20:12 UTC