[ZRH] Storage maintenance
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you that we carried out a scheduled maintenance at our storage cluster in the Zurich cloud location. The maintenance aimed at upgrading the OS version on several of the storage nodes. The duration of the maintenance works took 10 hours in total.

IMPACT:
No impact was exerted on any of the existing servers, drives or networking, other than a slight increase of the I/O operations for the duration of the maintenance window.

While it is important for CloudSigma to perform maintenances such as this to ensure the quality of our services, we do everything possible to minimize any inconvenience for our customers. We appreciate your patience and welcome any feedback.
Posted Sep 08, 2023 - 18:10 UTC
Update
CloudSigma would like to inform you that the maintenance works will be extended with additional 2 hours.
Posted Sep 08, 2023 - 15:59 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 08, 2023 - 08:00 UTC
Scheduled
CloudSigma would like to inform you that we are planning to perform a scheduled maintenance at our storage cluster in the Zurich cloud location. The maintenance aims at upgrading the OS version on several of the storage nodes. The planned duration of the maintenance works is ~8 hours in total.

IMPACT:
There will be no impact on any of the existing servers, drives or networking, other than a slight increase of the I/O operations for the duration of the maintenance window.

While it is important for CloudSigma to perform maintenances such as this to ensure the quality of our services, we do everything possible to minimize any inconvenience for our customers. We appreciate your patience and welcome any feedback.
Posted Sep 01, 2023 - 15:48 UTC
This scheduled maintenance affected: Zürich Cloud.