[RUH] Hardware Upgrade
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you that we performed hardware maintenance in our Riyadh cloud location. During the maintenance works, we replaced some failed drives within the cloud. The actual works took 1 hour in total.

All support activities were being conducted under the direct supervision of CloudSigma’s DevOps staff.

IMPACT:

There was be no impact on already existing/running customer’s virtual machines, hosts, network accessibility and/or any other running services.
Posted Jun 24, 2021 - 12:02 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 24, 2021 - 09:01 UTC
Scheduled
CloudSigma would like to inform you that we are planning to perform hardware maintenance in our Riyadh cloud location. During the maintenance works, we will replace some failed drives within the cloud. The actual works are planned to take no longer than 1 hour in total.

All support activities will be conducted under the direct supervision of CloudSigma’s DevOps staff.

IMPACT:

There will be no impact on already existing/running customer’s virtual machines, hosts, network accessibility and/or any other running services.
Posted Jun 23, 2021 - 12:01 UTC
This scheduled maintenance affected: Riyadh Cloud.