CloudSigma would like to inform you that the power maintenance of our infrastructure in the Clark cloud location was completed successfully. During the maintenance, we replaced capacitors and fan components of the primary UPS system.
IMPACT: There was no impact on any of the existing servers, drives, or networking, as our equipment has the required level of redundancy.
Posted Apr 23, 2025 - 09:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Apr 23, 2025 - 00:00 UTC
Scheduled
CloudSigma would like to inform you that we are going to perform a scheduled Power maintenance of our infrastructure in the Clark cloud location. During the maintenance, the DC will be replacing nearing end-of-life capacitors and fan components of the primary UPS system.
IMPACT: There will be no impact on any of the existing servers, drives, or networking, as our equipment has the required level of redundancy.