[WDC] Storage Cluster Maintenance
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you that the emergency replacement of SSD drives of our Storage Cluster, was completed successfully. The actual change took 90 minutes in total.
All support activities were conducted under the direct supervision of CloudSigma’s DevOps staff.
IMPACT:
There was no impact on already existing customer’s virtual machines, hosts, network accessibility and/or any other running services.
Posted Jan 09, 2018 - 15:37 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jan 09, 2018 - 14:01 UTC
Scheduled
CloudSigma would like to inform you that we will perform an emergency maintenance of our Storage Cluster, replacing some of the SSD drives. The actual change is scheduled to take 2 hours in total.

All support activities will be conducted under the direct supervision of CloudSigma’s DevOps staff.

IMPACT:
There will be no impact on already existing customer’s virtual machines, hosts, network accessibility and/or any other running services.
Posted Jan 08, 2018 - 19:43 UTC