[MNL]Host Upgrade
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to inform you that the scheduled maintenance in Manila has completed successfully.
Posted Sep 18, 2017 - 14:04 UTC
Update
CloudSigma would like to inform you that the Host Upgrade, we are performing now, is taking longer than the planned time. So the maintenance will be extended with two more hours.
Posted Sep 18, 2017 - 13:15 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 18, 2017 - 13:00 UTC
Scheduled
CloudSigma would like to inform you that we are planning to do scheduled maintenance of one of our compute Hosts. The actual change is scheduled to take no longer than 2 hours in total. The purpose of this maintenance is to update the Host OS which will improve the performance and stability.

All support activities will be conducted under the direct supervision of CloudSigma’s Operations staff.
Posted Sep 18, 2017 - 12:49 UTC