[FRA]Scale-Out Magnetic Storage Maintenance
Scheduled Maintenance Report for CloudSigma
Completed
CloudSigma would like to let you know that we successfully completed the Scale-Out Magnetic Storage Maintenance in our Frankfurt cloud.
Posted Sep 10, 2016 - 10:17 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 10, 2016 - 08:00 UTC
Scheduled
CloudSigma would like to inform you that we are planning to do a scheduled maintenance of our Scale-Out Magnetic Storage in Frankfurt. This maintenance is about fixing some bugs which we have noticed recently and adding some improvements within our storage system. The actual maintenance is expected to take no longer than 5 hours in total. During this time frame there should be no impact on already existing customer’s virtual machines, hosts, network accessibility and/or any other running services.

All support activities will be conducted under the direct supervision of CloudSigma’s devops staff.

IMPACT:
The actual maintenance is expected to take no longer than 5 hours in total. During this time frame there should be no impact on already existing customer’s virtual machines, hosts, network accessibility and/or any other running services.
Posted Sep 09, 2016 - 09:46 UTC